Customer:

HCI

Project Category:

Data Center and Large computer network hardware

Customer Requirement:

Design, Engineering services for the Electrical, Civil & Structural works of the 138kV substation and Transmission line including preparation of Technical specs, Bid evaluation and Vendor drawing review.

Project Result:

This is an ongoing project. This project was created to feed data center loads

What we did:

We have finalised the layout of the Substation and Transmission line. Nw the Structural design is commencing.

Project Description

To set up a 138/13.8kV Substation and Transmission line for 450MW Data Center

Project Budget:

2000000

Completion Date:

2026-10-31T00:00:00